West End Ferry Terminal Project faces review as bids soar $79M over budget
ROAD TOWN, Tortola, VI—With the lowest submissions of bids for the New West End Ferry Terminal Project far exceeding the project’s estimated budget of $15 million, an immediate reassessment of the project’s scope and requirements is being done.
Canadian & joint local firms submit bid for West End Ferry Terminal Project
WEST END, Tortola, VI- The Recovery and Development Agency (RDA) has announced that two bids have been received by the extended bid submission deadline, January 17, 2025, for the highly anticipated West End Ferry Terminal Project.
CDB gives go ahead to procurement process for WE Ferry Terminal construction
WEST END, Tortola, VI- The Virgin Islands Recovery and Development Agency (RDA) has received a "No Objection" from the Caribbean Development Bank (CDB) to advance the procurement process for the construction of the West End Ferry Terminal and temporary facility.
Local firms among 4 submissions shortlisted to bid for WE Ferry Terminal Project
WEST END, Tortola, VI– Four submissions were successful in the prequalification process and have been shortlisted to bid for the project to construct the new West End Ferry Terminal, according to the Virgin Islands Recovery and Development Agency (RDA).
9 firms submit bids to prequalify for West End Ferry Terminal rebuild
WEST END, Tortola, VI- Nine firms have once again submitted bids to participate in the pre-qualification process for the construction of the new West End Ferry Terminal, this time, by the August 31 deadline.
Portion of CDB loan to go towards new West End Ferry Terminal Project- VI Gov't
WEST END, Tortola, VI- The Government of the Virgin Islands (GOVI) has received financing from the Caribbean Development Bank (CDB) in an amount equivalent to US$65,291,000, and some will be allocated for the construction of the West End Ferry Terminal.
‘Classic Modern’ the winning design for new West End Ferry Terminal- RDA
WICKHAM’S CAY I, Tortola, VI- The Virgin Islands Recovery and Development Agency (RDA), today, Wednesday, December 28, 2022, announced the winning design for the new West End Ferry Terminal.
Construction of new WE Ferry Terminal to start later this year– Premier Fahie
WEST END, Tortola, VI- Premier and Minister of Finance Honourable Andrew A. Fahie (R1) has revealed that the construction of the new West End Ferry Terminal will get underway during the 2022 summer months.
German firm proposes organic futuristic design for WE Ferry Terminal
WEST END, Tortola, VI – More preliminary design plans for the new West End Ferry Dock in the Virgin Islands (VI) have indicated that the facility could feature futuristic green design elements tailored to the VI’s local climate with flood protection to account for rising sea levels.
'We don’t know how to build docks?' Skelton-Cline slams RDA
BAUGHERS BAY, Tortola, VI- Government Consultant and commentator Mr Claude O. Skelton-Cline has slammed the Virgin Islands Recovery and Development Agency (RDA) for issuing a contract to a foreign company for the design and construction management of the West End Ferry Terminal.