First 2 Sabbath Hill reservoirs fully rehabilitated

-first returned to service, while second scheduled for completion & commisisoning by Nov 30
The first 500,000-gallon Sabbath Hill reservoir has been fully refurbished, tested, disinfected and returned to service. Photo: Facebook
The second Sabbath Hill reservoir remains on schedule for completion and commissioning by November 30, 2026. Photo: Facebook
The second Sabbath Hill reservoir remains on schedule for completion and commissioning by November 30, 2026. Photo: Facebook
Director of the Water and Sewerage Department Mr Lyndon A. Hodge said completing the first Sabbath Hill reservoir is a major accomplishment and an important step towards restoring the facility to full operational capacity. Photo: GIS
Director of the Water and Sewerage Department Mr Lyndon A. Hodge said completing the first Sabbath Hill reservoir is a major accomplishment and an important step towards restoring the facility to full operational capacity. Photo: GIS
SABBATH HILL, Tortola, VI- The Ministry of Communications and Works has announced that the first two reservoirs at Sabbath Hill have now been fully rehabilitated and returned to service.

The first 500,000-gallon reservoir has been fully refurbished, tested, disinfected and returned to service, while the second reservoir remains on schedule for completion and commissioning by November 30, 2026.

The ministry said this marks a significant milestone in the ongoing water infrastructure maintenance and upgrade programme. 

The Sabbath Hill project includes the rehabilitation of two water storage reservoirs with a combined capacity of one million gallons, together with upgrades to associated piping, valves and site infrastructure.

According to the ministry, upon completion, customers will benefit from improved storage capacity, greater pressure stability, enhanced system resilience and a reduced risk of service interruptions. 

Director of the Water and Sewerage Department Mr Lyndon A. Hodge said, ”Completing the first Sabbath Hill reservoir is a major accomplishment and an important step towards restoring the facility to full operational capacity,”

50% operational capacity; expect interruptions

Until both reservoirs are fully operational, Sabbath Hill will continue to operate at approximately fifty per cent of its normal storage capacity. As a result, some customers may continue to experience intermittent disruptions to their water supply until the remaining works are completed and the facility's full storage capacity is restored. 

"We understand the frustration and inconvenience that continued water disruptions have caused for residents, families and businesses, and we sincerely apologise for the impact on daily life. While the completion of the first reservoir is an important milestone, we recognise that customers will not experience the full benefit of these works until both reservoirs are returned to service,” Minister for Communications and Works Hon Kye M. Rymer (R5) said. 

He assured that teams from the ministry and contractors are working diligently to complete the remaining repairs on schedule and restore the level of service that our customers expect and deserve.

Mr Hodge added that with only one of the two reservoirs currently in service, the system remains constrained and cannot consistently keep pace with demand across the distribution network, particularly during peak periods. 

“We remain focused on completing the second reservoir by the end of the month so that customers can begin to realise the full benefits of these improvements."

Leave a Reply



Create a comment


Create a comment

Disclaimer: Virgin Islands News Online (VINO) welcomes your thoughts, feedback, views, bloggs and opinions. However, by posting a blogg you are agreeing to post comments or bloggs that are relevant to the topic, and that are not defamatory, liable, obscene, racist, abusive, sexist, anti-Semitic, threatening, hateful or an invasion of privacy. Violators may be excluded permanently from making contributions. Please view our declaimer above this article. We thank you in advance for complying with VINO's policy.
Video Ad


Follow Us On

Disclaimer: All comments posted on Virgin Islands News Online (VINO) are the sole views and opinions of the commentators and or bloggers and do not in anyway represent the views and opinions of the Board of Directors, Management and Staff of Virgin Islands News Online and its parent company.